To ensure timely execution of different works an advance planning by the Departments is essential. The last quarter of a FY can be utilized for preparatory works including floating of tenders so that work orders can be issued in the first week of April of the next FY.
Departments having delegated financial power for according administrative approval up to Rs. 20 crores, tenders with less than 3 bidders can be accepted by the HoD up to Rs. 10 crores.
The Departmental Tender Committee shall be responsible for evaluation and recommendation of tender related works including but not limited to the following:
After finalisation of the tender process, the scope of work should not be increased during period of execution. No additional/ supplementary/ substitute items should be considered.
Additional Performance Security when the bid rate is 80% or less of the Estimate put to tender and no increase in scope of work of projects during execution phase.
To prevent unnecessary blocking of earnest money of the unsuccessful bidders, the bid evaluation committee shall carry out the financial evaluation of the tender just after financial bid opening (selection of L1 bidder) and all the unsuccessful bids shall be REJECTED.
Maximum financial powers for sanctioning any extra item or items, substituted item or items, and deviation in quantity or quantities at a time or one or two of it.
Deviation in quantities of individual item up to +10% of agreement quantities will not need any prior approval of technical sanction authority and sanction of deviations is not required.
Applicability of West Bengal Financial Rules for all Procurements and Works in all parastatals incl. procurements and works funded from their own source of fund.
Financial limit for technical vetting of any scheme for Sub-Assistant Engineers, Assistant Engineers, Executive Engineers and Superintendent Engineers will remain unchanged.
Bidders shall submit copy of a) Valid PAN issued by the IT Deptt., Govt. of India b) Valid 15-digit Goods and Services Taxpayer Identification Number (GSTIN).
Information on ‘Minimum period for submission of tender from the last date of publication’ should be furnished in Annexure-I of Memorandum No. 925-F(Y) dated 14.02.2017.
Starting Bid Price fixed by the Auction Inviting Authority is not confidential and shall be displayed at auction bid page against each item for information to the bidder.
All Tender Committees are hereby advised to upload the e-tender document by using 3 or 4 members DSC by selecting either (a) 2 of 4 or (b) 2 of 3 out of the available options.
There should normally be no post tender negotiations. If at all negotiations are warranted under exceptional circumstances, then it can be with L1, (Lowest tenderer) only.